Raw water is abstracted from the Tugela river via 16 No. 50mm NB stainless steel wellpoints.
A raw water pump on the river bank delivers raw water to the 30 kl/hour package treatment plant.

The treated water centrifugal pumps with a capacity of 45 kl/hr take water from the treated water balancing tanks and deliver it via a 4900m long 150mm NB steel/uPVC treated water rising main to the Sans Souci reservoir.

Location:
The farm Sunbury and the communities of Sans Souci and St Christopher, KwaZulu-Natal, South Africa.

Client:
Ilembe District Municipality

Key Resources:
Y Moodley: Pr Eng / S Swanby : PrTech Eng 

Project Value:
R 11,000,000

Date Completed:
2004